'Scrum fixed date planning, number of sprints

For fixed date planning with a 2 Weeks sprint, I will determine how many sprints I have between two dates, April 1, 2020, and June 4, 2020. The number of weeks between the two dates is 9, 1 weeks. Does this mean there are 4,5 sprints?



Solution 1:[1]

I advise that there is no such thing as half a Sprint and to round to a whole number. So, for your calculation, I'd say you have four Sprints.