'Scrum fixed date planning, number of sprints
For fixed date planning with a 2 Weeks sprint, I will determine how many sprints I have between two dates, April 1, 2020, and June 4, 2020. The number of weeks between the two dates is 9, 1 weeks. Does this mean there are 4,5 sprints?
Solution 1:[1]
I advise that there is no such thing as half a Sprint and to round to a whole number. So, for your calculation, I'd say you have four Sprints.
Sources
This article follows the attribution requirements of Stack Overflow and is licensed under CC BY-SA 3.0.
Source: Stack Overflow
| Solution | Source |
|---|---|
| Solution 1 | Derek Davidson PST CST |
