is there a possibility to add the field "Microsoft.VSTS.Scheduling.RemainingWork" on backlog level? I would like to have a field with remaining work in the backlog, so that the work can be entered there directly without creating a work item.
Azure DevOps Server version: Version Dev17.M153.3
I added following lines in Bug.xml:
<FIELD name="Verbleibende Arbeit" refname="Microsoft.VSTS.Scheduling.RemainingWork" type="Double" reportable="measure" formula="sum" />
<Group Label="Details">
<Control Label="Verbleibende Arbeit" Type="FieldControl" FieldName="Microsoft.VSTS.Scheduling.RemainingWork" />
<Control Label="Aufwand" Type="FieldControl" FieldName="Microsoft.VSTS.Scheduling.Effort" />
<Control Label="Schweregrad" Type="FieldControl" FieldName="Microsoft.VSTS.Common.Severity" />
</Group>
Solution 1:[1]
On the backlog, you can specify columns and the quick add panel configuration. Check this:
Use witadmin to import and export process configuration.